We are continuing to post updates of the progress. January Update: The Auditorium will not be completed until early/mid March. The High School musical is being postponed until early April. The dates have not been confirmed as of February 2nd. We anticipate the move to the new district offices occurring in APRIL of 2010, this is a change. We anticipate using the new Community Meeting room beginning in June. Dr. Huff and Dr. Pauly have been meeting with our principals and guidance counselors in anticipation of our Fall 2010 Distance Learning course offerings.Our roofers, masons, and grounds contractors are on hiatus until the spring.
Capital Project 2009 - 10 Cleveland Hill Union Free School District 105 Mapleview Road Cheektowaga, NY 14225-1599 |
|||||||||||||||||||||||||||||||
![]() |
![]() |
![]() |